Wednesday, September 19, 2007

MALKHED WATER SUPPLY-----SHAFT

MALKEED WATER SUPPLY SCHEME, TALUKA NER DIST. YAVATMAL
BRIEF NOTE ON USE OF SHAFT 1993
Use of shaft in place of ESR has been done first time at Malkhed village in Dist. Yavatmal. The Item was not included in the sanctioned scheme. But it was impossible to include ESR in the sanctioned scheme unless revision was proposed and sanctioned. Concept of BPT was already experienced and formulated in mind after the actual execution of Amaravati water supply scheme. Shaft concept was little modification of BPT having a rising main in the external M.S. pipe used as a shaft. The issue was discussed with Dr. Ingle while execution of Amaravati BPT. Due to problem of handing over of the Malkhed water supply scheme shaft was required to be constructed. Being the first effort of this kind thorough evaluation was required. It was decided to verify the discharge and pressures in the system. The results were informed to Dr. Ingle. He wanted to see the performance personally. Visit of Dr. Ingle and Dr. Dhabadgaonkar was arranged at Malkhed. He was happy to see the results, and appreciated the efforts. On the same day the scheme was handed over to the village Panchayat at the hands of Dr. Ingle. Brief details are given below. Numbers of shafts were erected in the District and everywhere the performance was excellent. Maharashtra Jeevan Pradhikaran had taken a note of the issue and circular was issued in favour of the application of shaft in small villages. After some years shafts as high as 26 m height were constructed at Amaravati and Trimbakeshwar and are still in use. Theoratical and construction aspects of shaft are given separately.

Malkhed Water Supply Scheme was sanctioned in the year 1985, costing Rs. 5.36 Lakh (gross). The execution was started from 1986 and by 1989 the schemes was put in to operation. The yield of supply well of this scheme is much more than the requirement of village. The work of GSR was completed in 1990. The site as per sanctioned scheme was required to be shifted due to Forest land. The GSR work was completed and supply through GSR was started from 4-2-1991. The discharge through stand posts was found on lower side in the opinion of villagers. To restore required pressure master pieces were introduced on the distribution lines, leading to low lying stand posts. There after some modifications were carried out in realigning of pipe lines. Then the village was divided into three zones, comprising of 3, 4 and 5 stand posts in each zone respectively.
After all above modifications, the supply was continued in last summer. Minimum required supply as per present norms i.e. 10 lit/min/tap was available on all stand posts by zoning.
However, the villagers were demanding E.S.R. Since, this work was not included in the sanctioned scheme; it could not be taken up. To get rid of this situation a tower of 7.8 m height is installed on GSR and the supply is now started through this tower. This has resulted in increasing pressure on all stand posts up to the satisfaction of villagers. Readings of discharge through all stand posts at every stage of improvement have been recorded and tabulated as per enclosed statement.
Though the yield of supply well is sufficient to fulfill the requirement of village at present, the work of under ground bandhara is completed in “summer – 1992” and a Gambian type bandhara is constructed is summer 1993.
Sanction cost of this schemes in Rs. 5.36 Lakh gross. Upto date expenditure incurred on this scheme is Rs. 4.94/- Lakhs up to March 1993, excluding cost of tower. Cost of tower and bandhara works out to Rs. 70,000 including all materials and labour. Thus from overall savings on the scheme, these works of tower and bandhara have been completed.
Advantages and dis-advantages of providing of shaft as against ESR may be narrated as below:
Advantages :-
1) Manufacturing and erecting time is much les than construction of ESR.
2) Cost is much low.
3) Supply to village can be started as soon as pumping starts. In ESR considerable time is required to fill up ESR.
4) Except storage, shaft serves the purpose of break pressure tank surge tank, and shaft type air valve etc.
Disadvantages :-
1) The only disadvantage is that there is no storage, as such power failure may interrupt the supply.
The only bottle-neck in this scheme was low pressure on stand posts. Erection of M.S. lower has solved this problem up to the satisfaction of villagers and village panchayat has immediately taken over the scheme on date 20-2-1993. The scheme is being run smoothly by village Panchayat.
EVAPORATION CONTROL
Evaporation control has been first time used as a conservation measure in water supply storage dam at Yavatmal. Yavatmal water supply scheme is maintained by Maharashtra Jeevan Pradhikaran up to consumer including collection of revenue. Economics of dam water evaporation control by spreading chemicals in urban water supply is quite different than that for irrigation. In 1992-93 to 1995-96 lot of experimentation was done during scarcity. The funds were allocated by the Science and Technology wing from Govt. of Maharashtra. Complete mathematical approach was developed and a payment was related to the actual water saved. While getting the effect of conservation of water expenditure on the process for the whole summer period, was found to be much less than the revenue at the normal domestic water rates realizable from the saved water. Cognizance of this experience was taken by Maharashtra Jeevan Pradhikaran and Govt. of Maharashtra and Evaporation control was considered as one of the measures of water conservation. A concept has been included in the Maintenance Manual of Urban areas published by CPHEEO. A detailed case study for Yavatmal water supply scheme has been separately given.
Evaporation is a continuous process and it can not be totally eliminated, but it can be controlled. It is a function of surface area and difference of temperature in the atmosphere and the water body. Evaporation action is vigorous at the surface. There is a loss of quantity of water due to evaporation, as at interface transformation takes place from liquid phase to gaseous phase.
As evaporation is increased with the temperature difference the areas where the atmospheric temperature is beyond 40 degrees the rate of evaporation is cognizable. In the summer period only, the water depth depletes by 1.5 to 2.0 m. Quantity of water lost will be the average surface area multiplied by the depletion depth of water. This becomes substantial quantity and saving of possible maximum quantity should be an attempt, where the water is scarce.
Evaporation being a function of surface area attempt should be made to minimize the surface area. Recently chemical has been evolved having long chain organic compound. These warer evapro retardants are having chemical composition of n-alcohols and n-alcoxy ethanols.
Water evapro retardants area available in paste form and are normally white in color. It can be brought in the form of liquid by mixing in water in fixed proportions and can be spread over the surface of water body. This being a long chain organic compound it forms a monomolecular film over the surface of water and it spreads automatically. The film is normally retained on the surface for more than 24 hours and needs to be replenished by spreading the chemical again. The film is transparent and the sunrays can pass through the same and aquatic life is saved. The chemical has been tested by National Chemical Laboratory, Pune and it has been certified as the non-hazardous chemical as far as drinking water is concerned.
Local factors affecting the control on evaporation process are as following.
1. Local temperature
2. Relative humidity
3. Wind direction, speed and diurnal cycles
4. Soil structure
5. Surrounding topography and vegetation pattern
The film is likely to be disturbed by wind and covering efficiency is affected. The film can be drifted in the direction of wind and this has to be taken care of by spreading the chemical periodically. Normal coverage area is 200 gm/hector, for daily application.
Considering all factors it has been observed that the control on evaporation can be attained to the extent of 25 to 33%. In case of a medium dam quantity of water saved is substantial and economic analysis has to be worked out in each drinking water supply scheme. In case of irrigation utilization this cost is not economical but in case of drinking water this cost may be comparable with the different alternative available for creation of new source.
Measurement of saving in water by using chemicals for control of evaporation is possible with the use of pair of standard pan evaporators. (Please refer relevant I.S.).
METHOD OF EVLUATION
Following daily observations are to be recorded.
a) Evaporation to the accuracy of 0.1 mm in two standard pan evaporators. Pan A for untreated and pan B for treated with chemical.
b) Physical water level of dam to an accuracy of 1 mm by means of dumpy level.
c) Max, min., pan A and pan B temperatures.
Procedure of further calculations,
1. A data table shall be created for dam levels and corresponding capacity.
2. Computer programme can be developed for the best fit equation from the data table, for converting levels into capacities and capacities into levels. Similar best fit equation can be found for transformation of levels into areas and vice-versa.
3. Select the pan factor which is normally ranging 0.8 to 0.9, according to site conditions.
Next day, the readings are taken for the make-up water required for maintaining the level of water in pan A and pan B. This is done by a standard calibrated metal jar. Quantity of water used for making up the levels in the standard pan evaporators is indicated in ‘mm’ depth.
Reading in pan A will be than pan B, because in pan B evapro-retardent chemical is used. Use pan factors for field conditions readings. As both the pans are kept near the dam water and in the same physical conditions maximum control of evaporations will reflect in reading of pan B. However the actual water level depletion will be more in the dam as chemical film coverage efficiency will not be 100% in the field.
Standard depletion statement for dam water levels should be used to obtain the available quantity of water in the dam after a defined period. For daily readings maximum accuracy is required.
In some of the cases it has been observed that daily quantity supplied to the town is less as compared to loss of water due to evaporation. When water evaporation retardants are used, at least 25% daily lost quantity is made available for next alternative use. It will give some revenue. It is good conservation of water.
During scarcity tanker supply may cost Rs. 40 to 80 per 1000 lit of water. However, evaporation control measures may bring down this cost to 10% of the tanker cost.
STEPS TO CALCULATE ACTUAL SAVING OF WATER
Actual saving of water can be calculated by careful observations of dam water levels and pan readings, at the specified timings. Normally, early morning period is chosen, to avoid wind effect. Waves on water surface create disturbance in taking readings of water level.. A cast iron TEE placed in water body as shown having a side entry of water and arrangement to measure the level depletion by using a metallic tape floating between guides. Reading can be taken against the cross wires. These readings can be accurate to 1 mm. Top of TEE can be connected to a TBM or to GTS bench mark. Accordingly, water level in the dam can be calculated daily. Position of TEE can be suitably shifted on lower side as the depletion continues in the dam water level. This depletion can be by evaporation or by use of water externally. The external use quantity daily can be known from pumping records or letting out water records. From these records daily use of water in terms of ‘mm’ depth can be converted when the area of dam water surface at that level is known. The graph is generally available but accurate surface area from that graph is not identified. Hence, a best fit equation is required to be developed. This equation is possible to be developed on computer. Once this equation is known computer can calculate ‘mm’ depth to area and vice versa. Similarly, relationship between ‘mm’ depth and capacity can also be developed. These can be utilized in preparing depletion statement.

EVAPORATION CONTROL

EVAPORATION CONTROL
Evaporation control has been first time used as a conservation measure in water supply storage dam at Yavatmal. Yavatmal water supply scheme is maintained by Maharashtra Jeevan Pradhikaran up to consumer including collection of revenue. Economics of dam water evaporation control by spreading chemicals in urban water supply is quite different than that for irrigation. In 1992-93 to 1995-96 lot of experimentation was done during scarcity. The funds were allocated by the Science and Technology wing from Govt. of Maharashtra. Complete mathematical approach was developed and a payment was related to the actual water saved. While getting the effect of conservation of water expenditure on the process for the whole summer period, was found to be much less than the revenue at the normal domestic water rates realizable from the saved water. Cognizance of this experience was taken by Maharashtra Jeevan Pradhikaran and Govt. of Maharashtra and Evaporation control was considered as one of the measures of water conservation. A concept has been included in the Maintenance Manual of Urban areas published by CPHEEO. A detailed case study for Yavatmal water supply scheme has been separately given.
Evaporation is a continuous process and it can not be totally eliminated, but it can be controlled. It is a function of surface area and difference of temperature in the atmosphere and the water body. Evaporation action is vigorous at the surface. There is a loss of quantity of water due to evaporation, as at interface transformation takes place from liquid phase to gaseous phase.
As evaporation is increased with the temperature difference the areas where the atmospheric temperature is beyond 40 degrees the rate of evaporation is cognizable. In the summer period only, the water depth depletes by 1.5 to 2.0 m. Quantity of water lost will be the average surface area multiplied by the depletion depth of water. This becomes substantial quantity and saving of possible maximum quantity should be an attempt, where the water is scarce.
Evaporation being a function of surface area attempt should be made to minimize the surface area. Recently chemical has been evolved having long chain organic compound. These warer evapro retardants are having chemical composition of n-alcohols and n-alcoxy ethanols.
Water evapro retardants area available in paste form and are normally white in color. It can be brought in the form of liquid by mixing in water in fixed proportions and can be spread over the surface of water body. This being a long chain organic compound it forms a monomolecular film over the surface of water and it spreads automatically. The film is normally retained on the surface for more than 24 hours and needs to be replenished by spreading the chemical again. The film is transparent and the sunrays can pass through the same and aquatic life is saved. The chemical has been tested by National Chemical Laboratory, Pune and it has been certified as the non-hazardous chemical as far as drinking water is concerned.
Local factors affecting the control on evaporation process are as following.
1. Local temperature
2. Relative humidity
3. Wind direction, speed and diurnal cycles
4. Soil structure
5. Surrounding topography and vegetation pattern
The film is likely to be disturbed by wind and covering efficiency is affected. The film can be drifted in the direction of wind and this has to be taken care of by spreading the chemical periodically. Normal coverage area is 200 gm/hector, for daily application.
Considering all factors it has been observed that the control on evaporation can be attained to the extent of 25 to 33%. In case of a medium dam quantity of water saved is substantial and economic analysis has to be worked out in each drinking water supply scheme. In case of irrigation utilization this cost is not economical but in case of drinking water this cost may be comparable with the different alternative available for creation of new source.
Measurement of saving in water by using chemicals for control of evaporation is possible with the use of pair of standard pan evaporators. (Please refer relevant I.S.).
METHOD OF EVLUATION
Following daily observations are to be recorded.
a) Evaporation to the accuracy of 0.1 mm in two standard pan evaporators. Pan A for untreated and pan B for treated with chemical.
b) Physical water level of dam to an accuracy of 1 mm by means of dumpy level.
c) Max, min., pan A and pan B temperatures.
Procedure of further calculations,
1. A data table shall be created for dam levels and corresponding capacity.
2. Computer programme can be developed for the best fit equation from the data table, for converting levels into capacities and capacities into levels. Similar best fit equation can be found for transformation of levels into areas and vice-versa.
3. Select the pan factor which is normally ranging 0.8 to 0.9, according to site conditions.
Next day, the readings are taken for the make-up water required for maintaining the level of water in pan A and pan B. This is done by a standard calibrated metal jar. Quantity of water used for making up the levels in the standard pan evaporators is indicated in ‘mm’ depth.
Reading in pan A will be than pan B, because in pan B evapro-retardent chemical is used. Use pan factors for field conditions readings. As both the pans are kept near the dam water and in the same physical conditions maximum control of evaporations will reflect in reading of pan B. However the actual water level depletion will be more in the dam as chemical film coverage efficiency will not be 100% in the field.
Standard depletion statement for dam water levels should be used to obtain the available quantity of water in the dam after a defined period. For daily readings maximum accuracy is required.
In some of the cases it has been observed that daily quantity supplied to the town is less as compared to loss of water due to evaporation. When water evaporation retardants are used, at least 25% daily lost quantity is made available for next alternative use. It will give some revenue. It is good conservation of water.
During scarcity tanker supply may cost Rs. 40 to 80 per 1000 lit of water. However, evaporation control measures may bring down this cost to 10% of the tanker cost.
STEPS TO CALCULATE ACTUAL SAVING OF WATER
Actual saving of water can be calculated by careful observations of dam water levels and pan readings, at the specified timings. Normally, early morning period is chosen, to avoid wind effect. Waves on water surface create disturbance in taking readings of water level.. A cast iron TEE placed in water body as shown having a side entry of water and arrangement to measure the level depletion by using a metallic tape floating between guides. Reading can be taken against the cross wires. These readings can be accurate to 1 mm. Top of TEE can be connected to a TBM or to GTS bench mark. Accordingly, water level in the dam can be calculated daily. Position of TEE can be suitably shifted on lower side as the depletion continues in the dam water level. This depletion can be by evaporation or by use of water externally. The external use quantity daily can be known from pumping records or letting out water records. From these records daily use of water in terms of ‘mm’ depth can be converted when the area of dam water surface at that level is known. The graph is generally available but accurate surface area from that graph is not identified. Hence, a best fit equation is required to be developed. This equation is possible to be developed on computer. Once this equation is known computer can calculate ‘mm’ depth to area and vice versa. Similarly, relationship between ‘mm’ depth and capacity can also be developed. These can be utilized in preparing depletion statement.

BAROMETRIC LEG CHLORINATOR

Barometric Leg Chlorinator
This is the simple form of chlorinator having no moving parts. It works on hydraulic balancing of a gas in small diameter PVC pipes.
Chlorine cylinder or tonner can be connected to the chlorinator assembly as usual by a glass reinforced plastic tube. Chlorinator assembly consists of a 20 mm diameter PVC pipe (Plumbing type) taken to 10 m height from the tonner center and then it is taken down to the floor level. A down take water pipe 25 mm diameter PVC pipe is connected to the gas pipe at floor level. Water pipe is having a constant head of 4 m, which has been ensured by providing a water tank of 100/200 lit capacity. FSL of this tank is maintained by providing water flow continuously preferably through two different sources. Overflow should be continuous and can be directed to P.W. Sump.
Gas and water can be taken to P.W. Channel or to suitable location of dosing in a leading PVC pipeline of 32 mm diameter having a minimum length of 40 m approximately. At the dosing point a reducer of 32 by 20 mm shall be provided to ensure a smooth flow of solution at the dosing point.
Water down take pipe shall have a parallel open ended equal branch off taking from 2 m height from floor level and reaching up to FSL of water in tank. Gas pressure and water balancing can be seen in the transparent pipe.
Upper portion of the branch can be a glass tube or a transparent pipe. For a specific opening of tonner valve a balancing of water is specific and can be calibrated to PPM dosing in PW Sump. The calibration can be suitably marked on the tube, by taking different working trials.
Gas has to enter in the system through a 10 m high pipe. In case of emptying of the tonner suction can be created and water can have an access in the tonner. However, this is avoided, because of the fact that water can not rise in pipe beyond 10 m from the gas water connection point which is at floor level. Hence, the safety is ensured.
Advantage of barometric leg chlorinator:
a) Capital cost is less
b) Functioning is easy
c) No moving parts
d) Works on simple hydraulic principles
e) Repairs are easy and economical
f) Safe in handling
g) Process is easily understandable
Modifications in the system have been done to facilitate better functioning. Alarm has been introduced for checking the level in the water tank. Further a tube scrubber has been introduced to ensure better mixing of gas in water. Very effective tools have been introduced for controlling valves of the tonner.
This system has been successfully used at number of places in Maharashtra and Govt. of Maharashtra has recommended this system to be adopted in municipal water supply.

HORIZONTAL FILTERS

HORIZONTAL FILTER – CONCEPTS AND APPLICATIONS
A new application introduced in Maharashtra Jeevan Pradhikaran for the upgradation of the existing facilities. The first such experiment was done at Amaravati at Wadali treatment plant. This was created in 1955 but it was not in use since 1960. During scarcity period of 1984-87 Amaravati city required water from all possible sources. A complete renovation was taken up for Wadali plant. For reducing turbidity of raw water from Wadali tank this type of filter was externally introduced. It was found to be successful. This was appreciated by the then Chief Engineer. After this attempt lot of modification were done in the field application based on the actual experience. Opportunity was available to work in the drought prone areas of Amaravati ,Yavatmal and Satara districts. In 1997, while on training in IRC, The Netherlands these modifications could be discussed with the team of experts working on the same subject. All applications were much upheld by the team. To cover all these concepts and also sharing the practical experiences for the Horizontal Filters a paper was presented in a National seminar on New Technology in Water Supply convened by CPHEEO.

1. GENERAL
When Water flows through a filter media, its turbidity is reduced. Filer media naturally available is surface of earth. Rain Water percolates into the soil and then flows from higher elevation to lower elevation. At some point it may come out in the form of spring. This water is very clear in terms of turbidity. During the flow it has a straining action. Filtering area is enormous. Hence, rate of filtration is very low. The action of filtration is also very slow. But the flow is established naturally due to potential difference.
2. MAIN TYPES OF FILTERS
In case of artificial filters there are mainly two types. When water flows from top to bottom through a filter bed, it is a vertical filter. Straining action is through the filter media provided. Rate of filtration, which may be predetermined, goes on diminishing as the filter run is increased and re-stabilization of the filter bed is necessary. Rate of filtration is inversely proportional to the loss of head through filters.
The second type of filter is naturally available or horizontal filter. It can also be created artificially. Water is allowed to enter horizontally through the artificially filled media. In this case also straining takes place. During the flow loss of head is also created. When the loss of head exists straining is effective and filtrate water quality is improved. In this case Velocity of water is very less. It is proportional to loss of head. The rate of filtration is also very less. It is inversely proportional to loss of head.
3. BASIC CONCEPTS OF HORIZONTAL FILTERS
AB and CD are perforated partitions and the media is held in ABCD Boundaries, then water will find its way through the media by adopting any circuitous path. Naturally, the resistance is created by the media. The resistance depends upon the fineness of media; its travel length, and voids in the media. Due to resistance in the media, there is some loss of head. Flow exists through the media. Turbidity existing in the inflow water has to pass through media. It has to cross the barriers in the random way. In the process water being more generous to get through the media, discrete turbidity particles lag behind and in the process gets settled on the surface of the media. This process attracts more turbidity particles and water moves faster rubbing the surfaces and a sort of turbid layer is formed on the media surface. This builds up more resistance of the same media. Process of adsorption is also effective as the time passes on. If the water level of the incoming water is fairly constant, the drawl of water is continuous, unless on the surface CD full resistance has not been developed, flow, is varying according to the effective resistance of the media. Process can be made effective, if the rate of filtration is kept minimum. Recommended rate of filtration is 2.5 to 3 m3/m2/hr. When the filter gets choked, the flow stops, if there is a space above media, parallel to ‘AC’ the water does not flow through filter, but short circuiting is observed and it runs over the media and in that case unfiltered water is observed at the outlet.
4. ARRANGEMENT OF HORIZONTAL FILTERS
Use of Artificial horizontal filters can be done effectively, with the basic concepts of horizontal filters are known. Keeping rate of filtration to the limits 2-5 to 3m3/m2/hr. media boxes can be constructed. Size of media, at least in the first box, shall be more than 25mm for obvious reasons. The flow should be established through the media. The important consideration is, what should be the of optimum length. In case of artificial filters, there are limitations of depth of maximum 1.5 m. In that case, the size of box will have limitations of 1.5x1.5x1.5 m. It gives sectional area of maximum 2.25 sq. m. From this sectional area maximum possible flow desirable is 2.25 m2 3m3/m2/hr i.e. 6.75 m/hr. or 6750 mm/hr. For having minimum flow time through filters, the length of the filter may be equivalent to 15 min. Thus, it will be 6750 mm/4=1687 mm limited to 1.5m. This will ensure slow flow through the media. In the first chamber, however, the flow will be faster initially as only coarser media is placed in the chamber. If total travel time is prolonged, still better results are expected. Further, if the adjoining chamber is filled with media of size 25 to 12 mm, then flow rate is restricted and more head loss is expected. Size of this chamber is also kept as 1.5x1.5x1.5 m. If both these chambers are followed by another box of 1.5m x 1.5m x 1.5 m. size and filled with media of size 12 mm to 6 mm, then flow rates are further restricted. Actually ultimately the Governing rate of filtration is the result of flow through period in the finest media. In the initial chambers flow is obstructed and it gives more settling time to U/S water as compared to that in the finest media. Total length of filters is about 4.5 m and water has to flow from coarser media to finer media.
Connected horizontal boxes –
In this case maximum resistance is in the third box. It governs the detention time in the boxes as a whole. First & second chamber losses are less as compared with the third. As retention time in the first & second chamber is more due to higher resistance in the third chamber, a slow settling action also starts. Progressively the flow of water in these boxes is stabilized and comparatively clear water comes out through the third box.
As regards the percentage volume of voids in the three equal boxes, there is no major change. But due to use of finer media the surface area of media is increased. As the depth of the box is 1.5 m, up to which media is filled. The maximum expected head loss is limited to 1.5 m. Hence, if the driving head is insufficient for water to come out of these boxes, naturally there is heading up of water. If heading up of water is more, the driving force is more and hence flow is more. For this heading up of water in the upstream water containers, channels, boxes should have space above, otherwise the water will prefer to overflow than to flow through the strained path. This can be controlled by providing larger area or adding no. of boxes in parallel.
5. MODIFIED ARRANGEMENT OF BOXES
Sequential straining through finer medias in series are definitely giving good results but the frequency of choking the boxes and cleaning thereafter is much more. It is required to watch the process closely, otherwise there are chances that water tring to overflow or flow on top of filters, rather than through the filters. To avoid this, following modifications were thought of and carried out in field.
Coarser and finer media, instead of grading sequentially in the series, in boxes, to follow, they are arranged in one box and such boxes are kept in series with a hydraulic separator in between in the consecutive boxes. Total length of media (effective) is kept constant i.e. 4.5 m.
If the discharge is up to 5 m3/m2/hr. the results in above mentioned horizontal filters are very encouraging. The step by step action in this filter is as following,
a) Incoming flow has lesser resistance through coarser strip. It increases in the medium graded media strip and has the maximum straining action through the finer media. As the resistance is built up upstream box level rises; and being initial box, it is at its maximum level.
b) The stained flow eases out while coming out of the box. It reaches to the blank box and due to drop in gradient, levels at the bottom. It tries to find thorough access in the media box. Due to relative resistance, it tries to rise up in the blank box, till it matches with head loss in the initial box below the original level of water before entering the initial box. After reaching this level, water has no option to find access through the next media box.
c) The process continues in the media box and the blank box in series.
d) It is normally found that in the fourth blank box the resulting water level is substantially below the original level.
6. OBSERVATIONS
The following observations are seen in the field.
a) When flow is stabilized, total incoming flow is equal to total outgoing flow though whole filter.
b) The quality of water is sequentially improved in the blank boxes.
c) There is continuous drop in the water levels in the blank boxes in sequence.
d) Improved quality is proportional to the drop observed.
e) Choking of filter starts in the initial box. It steadily drops the level in blank box.
f) Choking is governed by the incoming turbidity of water. For normal surface water turbidity is up to 50 ppm. The filter box gets choked in a specific time. It is required to take out media, clean with water and refill in the same fashion.
g) Frequency of choking of filters down stream is delayed sequentially.
h) Manual washing of filters can be taken up after specific time for the initial box and one box downstream in rotation.

7. WELL IN WELL TYPE ARRANGEMENT
For rural Water Supply, if the above type of filters are followed after due pre-settling, the results are much better as the incoming turbidity is much within the limits. Typical arrangement of box type of filters, used in rural water supply schemes is shown as below,
According to requirement the sizes of sump can be chosen. However, the above mentioned sizes are more workable. No. of boxes should be minimum 5 No. filled with media. More No. may be suitable, but they do not add to performance. Media boxes are separated by providing openings in the separator walls. Opening area should be minimum 35% of the total cross section surface. Openings should be evenly distributed.
There should be no openings in the top 20 cm depth. From the last box, the water is allowed to enter into sump.
As there is storage in the sump, the water level rises & this in turn checks the relative head loss through the filter boxes. Pumping should be simultaneous. Then the hydraulics is easily be balanced.
In the case of gravity systems, the upstream flow can be controlled but in case of pumped systems the upstream flow should match with the pumping from sump.
8. ARRANGEMENT FOR RIVER INTAKES HAVING LESSER SURFACE FLOW IN SUMMER

When the supply wells are situated on the banks of rivers, normally, the yield in fair seasons is sufficient to cope up with the demands of village. But in the summer, the yield drops down suddenly and the same pump can not work continuously. It results in the shortage of water in comparison with the grown up water demands in the summer period. Hence, the reliability of water supply scheme comes down and users are dissatisfied.
In such case, appropriate size horizontal filters can come to help. These filters can tap surface/subsurface flow from the river and connect it to the supply well. During its horizontal travel the water is filtered through the media. As these filters are hydraulically connected to the supply well; the rate of filtration is equal to the maximum of rate of pumping. However, in the normal working the quantity of water through filters is only to the extent of difference between rate of pumping and the yield of well.
In this slow filtration process, choking of media in the first box is possible. However, cleaning period can be much longer. This can be equivalent time of the peak summer, when the use of filter is really necessary.
With the commencement of rainy season these filters can be isolated by sluice valve. This also avoids turbid water getting into the supply well. During summer, however, the turbidity is well within the range of requirements of operation of these filters.
Many supply wells are rejuvenated with the introduction of these filters and round the year reliability of water supply is assured.
Though, theoretically only 3 media boxes are necessary to give the required output, practical considerations have shown that 5/6 media boxes give better results. (Total 12 to 14 boxes, including hydraulic separators), However, the media size can be increased. to 40 to 50 mm metal can be used as coarser media and 12 to 20 mm can be used as finer media. These sizes can work up to 15 m3/m2/hr. rate of pumping.
Disinfection by use of chlorine or bleaching powder is however, must be associated with this system; to ensure quality of water.
These filters can be cleaned manually or by using water jets. As the boxes are closed from top by pre-cast strips of slabs, they are well protected in rainy season and in floods. As the boxes are more or less flush to the natural bed of the river, they are not disturbed during floods.
Approximate construction cost of this arrangement of filter is Rs. 70,000/- excluding the cost of connecting pipe as its length is variable as per the site condition.
The construction can be done in a period of 30 days when the river flows are very less in the summer.
9. COMBINATION OF DWARF BARRIERS ACROS RIVERS AND USE OF HORIZONTAL ROUGHENING FILTERS FOR SURFACE INTAKES-
As shown above, the method used for Rural Water Supply wells connected to surface/subsurface waters of Rivers by horizontal filters, it can be applied to small Urban Water Supply schemes. Main difference in application is, in case of Rural Water Supply, horizontal filter is required to act as a on line treatment unit of filtration, where as the Urban Water Supplies are having a separate water treatment unit. Hence, the contribution by horizontal filters, in case of Urban Water Supply is to act as a pre-treatment unit.

In the summer, the flows in rivers are very less. It becomes difficult to get sufficient water through intakes. This is still more difficult, if it is intended to construct a horizontal filter unit connecting river and jack well. For this purpose and to create a small balancing storage to cope up with summer demands, a dwarf barrier of about 1.2 to 1.5 m height can be easily created across the river. This will not only create the storage but increase the intake water level. It will further facilitate assured intake through Horizontal filter. In the equilibrium stage, level in the jack well and the storage in dwarf barrier will be the same. When the pumping is started, it will create flow through filters at the equivalent rate of pumping. In the process there will be straining action in the filters and head loss will occur along the flow path through filters. It will arrest the turbidity in the incoming water, and comparatively clearer water will reach jack well. In the process initial boxes of horizontal filter will choke. They are required to be cleaned periodically. Water jets can be used for cleaning by connecting pumping systems from jack well. If required, a small drain from blank box can be provided.
Advantages claimed in this process are as following.
1. Jack well silting time is prolonged. It remains comparatively cleaner.
2. Pumping machinery, impellers ensure longer life, as wear & tear with sand, silt and turbidity is comparatively less.
3. Turbidity load is not transferred to Treatment plant and hence the Treatment process can be simpler. Filter runs are increased.
4. The turbidity particles which are carried up to Treatment plant are finer and due to rubbing action the nature of turbidity is changed and settling is easier.
5. On line horizontal filter replaces connecting pipe. Hence, additional cost involved is much less.
6. Periodical cleaning by water jets or manually is possible and chocked turbidity/silt can be washed out and excluded from entering into the main system.

7. When turbidity loads are reduced, the economy is achieved by less use of chemicals in the Treatment Plant.


Pumping rates in semi urban or small municipal council water supply schemes are comparatively larger than those in Rural Water Supply Schemes. Hence, the rate of filtration through horizontal filters is larger. The filters with finer media will not cope up with these flows, even if battery of filters is used. Hence, only coarse media of 50-40 mm is used in such type of filters. No. of boxes can suitably be increased. Filter rates up to, 100 m3/m2/hr. can be used with this media size. The effect of pre-filtration unit is, however, very encouraging. For better control in cleaning operations, sluice valves can be fixed at the starting and at the end of filters. As the filter boxes are closed from Top, by RCC Strips of slab, the media does not get disturbed even in the floods. However, care is required to be taken, when the flood recedes. Hence, the appropriate pitching of the area is required to be done.
10. HORIZONTAL FILTERS AHEAD OF SEDIMENTION PROCESS
In some of the Rural water supply schemes regular filtration process is avoided and only settled water is supplied. As the process of filtration requires maintenance of a skilled person and the same is not available in the remote rural areas, the process is not provided. In such cases the horizontal filters can supplement further treatment to sedimentation. Instead of constructing separate filter unit, use was made to upgrade the system by constructing horizontal filters along the existing masonry benches. The hydraulics from settling tank to P.W. sump is not disturbed, only the water travel was changed from closed conduit to through Horizontal filters to give the desired results.
11. WORKING EFFICIENCIES
In all the applications shown above it is necessary to emphasis that Horizontal filters can work efficiently, but they are required to be maintained properly. The maintenance is not nullified, nor it is pleaded that the system is totally maintenance – free. However, it can be said that the maintenance required is tangible and understandable to the supervisory staff. Highly skilled operation or any specific trained operators are not required. The process of maintenance is simpler and found to be accepted by the villagers.
Cleaning period is required to be watched and decided in each case separately. It can range from monthly cleaning of boxes for the horizontal filters used for Rural Water Supplies where no other treatment is included in the process. This cleaning time can be bimonthly in case of Roughening filters for river intakes. However, in any case when the incoming turbidity is more, in rainy season, the cleaning interval is closer. In some cases the horizontal filters are not used in rainy season, as the supply wells yield sufficient water in rainy season.
Regarding the bacteriological efficiencies, proper evaluation is not yet done, but experiments in other countries reveal that with filtration rates up to 4 m3/m2/hr,. the bacteriological efficiency is up to 75 to 80%. However, for all practical purposes, if disinfection is followed by the horizontal filter units, it will take care of removal of remaining bacteriological loads.
For small urban communities and Rural areas maintenance can safely be relied upon with the use of horizontal filters. Even if, there are no set standards of maintenance, the choking of filters is immediately reflected in Overflowing of the units as well as carrying of turbid particles in system, and restoring action becomes obligatory.

12. REVIEW OF WORKS IN THE COUNTRY AND ABROAD
All India Institute of Hygiene and Public Health, Calcutta, has carried out extensive studies on horizontal filters and further finer Treatment by slow sand filters. Turbidity removal is very effective in horizontal filters. Rated treatment capacities are reported up to 2m3/hr/m2 with 50 to 75 ppm Raw Water turbidity. The recorded cleaning period is 140 to 160 days. No chemicals were used and the turbidity removal was to the extent 80 to 85%. Coliform removal is also reported up to 90% minimum. Though HRF is not complete treatment, it is definitely a most appropriate pre-treatment in semi-urban areas and appropriates treatment in Rural areas.
International Reference centre reports that Mr. M.Wegelin has prepared Horizontal flow roughing filtration (HRF), manual for Design, construction and operation. (IRCWD Report No. 06/86). Lot of research in Laboratory and field has been done. Evaluation results have been reported from the works done in Colombia, and Research centre in CINARA. Horizontal roughing filters, is technically known as multistage filtration. They are slightly modified to Dy. RF, known as Dynamic Roughening filters. These are specially taken up for research by International Institute for Infrastructures, Hydraulic and Environmental Engineering in Delft and the University of Valle Cali, Columbia. Dy. RF is especially useful in dealing with variant turbidities and has proved to be very successful pre-treatment. They have reported that about 2.20 person –hrs are required for Manual cleaning, washing, backfilling per Sq.m of Dy. RF. Feasible filtration rates may be up to 7 m3/m2/hr but efficiency of filtration is satisfactory up to 4 m3/m2/hr. Turbidity removals up to 66%, suspended solids removal upto 93% and faecal coliform removal up to 95% have been reported.
Recently research is being done on URFS i.e. roughing filters in series. Manual cleaning is a sort of thing which is not so appropriate in the Treatment process. If not avoided, it can be minimized by the introduction of URFS. The silt storage capacity of URFS is limited and therefore the units are required to be cleaned regularly by draining the units. In URF the most of the sludge remains at the bottom & can be easily drained out. The wash Water required is also comparatively less. It is found that the URFS is more efficient system to handle the treatment process in the Rural Areas. During the initial stages of Research alum was being used in very low dosages, say up to 1 ppm, but with horizontal flow roughing filters or Upward flow roughing filters in series alum dosing ins not insisted.
13. CONCLUSIONS
Horizontal filters as applied in Yavatmal and Amravati Districts of Maharashtra are required to be extensively used wherever suitable. It has variety of applications. The construction is simple and no specific requirement of special material is necessary. The operation & maintenance can be done by unskilled labour and the whole process is economical. Particularly, in river as a source the combination of dwarf storage barriers and Horizontal filters works very satisfactory.
Horizontal filters used as a pre-filter unit is also useful in semi-urban areas. The design for sizes, use of construction materials, choice of filter media, cleaning time backfilling procedure and everything regarding horizontal filter is very simple to understand, and anyone who has once used these filters, have a tendency to apply the same in one form or the other, in the next opportunity he will get for similar execution of works. He can easily decide all the parameters of application.
It is true, that the thorough evaluation of the working of horizontal filters, already constructed have not been done systematically up to now. All technical parameters are not checked and the performance is certified. This work is required to be taken separately by the organization or any educational institute. However, as it has helped to solve the problems of source augmentation, surface water treatment, pretreatment, the process available for application has been put forth. Constitution of HRFS and its arrangement has been evolved by actual field experience, by working out better alternatives. Providing a blank box in the consecutive media boxes works out to be more useful and has been tried successfully. This has not been referred to in the Literature and reported practices in this area.
14. ACKNOWLEDGEMENTS
I am grateful to Shri. R.M. Sagane, Member Secretary (Tech), Maharashtra Jeevan Pradhikaran for having personally inspired for taking up such works in Yavatmal District. The above said compilation of field experience is also due to him. I am also thankful to my co-workers in Yavatmal and Amravati District, for having sincerely done their job in the various applications of Horizontal filters.

Tuesday, July 24, 2007

TOTAL GRAVITY WATER SUPPLY SCHEME IN THE RECORDS

TOTAL GRAVITY WATER SUPPLY SCHEME IN THE RECORDS

Recently 156 villages Regional Rural Water Supply Scheme in Maharashtra has been placed in the LIMKA BOOK OF RECORDS. It is the largest Regional scheme in India operating under 100% gravity It is giving benefit of water supply to about 400000 souls in the saline track. Distribution of water is through house connections and thereby getting the higher level of service. Revenue collection is more than 80%of the assessment. The scheme is running in profit. A review of physical details are have been taken along with some salient features.

Background
Three districts namely Amravati, Akola and Buldhana are situated in the basin of River Purna covering an area of 4692 Sq.km. is mostly saline. The under ground water in this area is much saline and unsuitable for human consumption. This belt has covered about 812 villages from these districts. The 156 villages RRW scheme is meant to take care of the area /villages and towns from Amravati district.
The covered villages and towns are situated in Daryapur, Anjangaon Surji and Bhatkuli Talukas of Amravati District. In this area no sweet water was available except seasonal surface water of river. Purna, Chandrabhaga, Sapan, Bordinalla and Bhuleshwari are the main rivers. They partially fulfilled the requirement of drinking water. In past, most of the rivers were perennial and they fulfilled the total requirements of drinking water of all the inhabitants. Regional rural water supply schemes were executed for this area in the year 1964 to 1969 by dividing the area in five groups with different sources, such as Tube wells, supply wells, surface water with Treatment plant, Infiltration wells, with network of A.C. pipelines and service cisterns.

Since last few decades due to scanty rainfall all the rivers in the area go dry in early summer, which resulted in augmentation of sources, year by year. Number of tube wells and infiltration wells were constructed in command area. As per chemical analysis, quality of water supplied to the villagers from these sources was brackish, but there was no alternative source to fulfill the requirement. Network of service lines was of Asbestos Cement pipes. Number of leakages was a feature during supply and hence tail-end villages continue to suffer for a long period. It resulted in morchas and agitations by the thirsty villagers. Also, water supply was getting suffered due to pump failure, load-shading etc.

Operation and maintenance of all these Regional schemes was a tedious job and expensive. No special grants were available for maintenance of these schemes. Since beginning all these Regional schemes were under maintenance of Maharashtra Jeevan Pradhikaran. Due to uncertain supply there was no recovery from villagers as panipatti. Also, recovery was the responsibility of Zilla Parishad, Amaravati. To avoid all these problems a scheme was proposed from Shahanoor dam as a source and having all metallic leading mains for 156 villages and two towns and was submitted to Govt. in the year 1997. Due to some technical changes and cost revision, it was approved in the year of 1998. Details of proposed schemes are given as below.


Anjangaon and Daryapur Towns

The covered towns i.e. Anjangaon Surji and Daryapur were served from individual schemes having supply wells on the bank of river Shahanoor and Chandrabhaga. This scheme was implemented in the year 1983 and 1970 respectively.
Due to scanty rainfall, original source of both the schemes resulted in very poor yield. Source augmentation was done by providing number of tube wells and other necessary pipeline and pumping machinery. Anjangaon Town water supply scheme, since its execution is under maintenance with Maharashtra Jeevan Pradhikaran. It is having metered connections and Pradhikaran is collecting revenue.
Sources of Daryapur Town emergency water supply scheme i.e. number of tube wells were located about 25 km from Daryapur town, and the leading line from these sources, was of 300 mm diameter Asbestos cement pipe, partial Cast iron pipes, and partial PVC pipes. Due to number of leakages and failure of power supply, system provided erratic and unreliable water supply. Frequency of this supply was uncertain. Daryapur town water supply scheme was under maintenance with Municipal Council Daryapur. This maintenance was continuously in loss.
Daryapur and Anjangaon towns had the same source i.e. Shahanoor dam as that of 156 villages. It was not appropriate to have parallel lines from same source leading to two towns and to 156 villages. The treatment plants could also be combined.
Hence, both the towns were covered in combined water supply scheme. Combined water supply scheme was the only minimum cost solution to fulfill the daily demand with safe drinking water to beneficiary inhabitants with sufficient quantity of water supply. Government of Maharashtra had considered the combined water supply scheme proposal and it was specially approved for both the towns and 156 villages located in saline area of Amravati district. Irrigation Department approved the reservation of water to the extent of 12.45 MCUM in Shahanoor Dam, which is having a live storage of 45 MCUM.

Combination of Scheme: - Individual schemes were submitted for Anjangaon, Daryapur and 156 villages with source as a Shahanoor Dam. To avoid repetitions of Pipelines, treatment plant etc. combined scheme was proposed and the Govt. approved it. It resulted in saving of Rs. 82.63 crores, shown as below,
Cost of Anjangaon Town W.S.S. Rs. 31.58 Crore
Cost of Daryapur Town W.S.S. Rs. 44.21 Crore
Cost of Regional W.S.S. for 156 villages Rs.169.15 Crore
Total cost of the individual schemes Rs.244.94 Crore

Total cost of the Combined schemes Rs.162.31 Crore
Net Saving due to combination Rs. 82.63 Crore

To avoid the institutional problems of maintenance, Govt. approved the proposal to maintain the scheme by Maharashtra Jeevan Pradhikaran. This has happened first time in the state.



Details of the scheme.

1. Source Shahanoor Dam Medium Irrigation Project.

2. Date of Administrative approval 15.10.1998

3. Date of Technical Sanction 09.01.1999

4. Gross cost of Scheme 162.31 Cr

5. Gross cost of scheme with Escalation 181.16 Cr

6. Designed Population (Urban & Rural) 424022 souls (2031)

7. Rate of supply for Anjangaon Town 100 to 125 lpcd
Daryapur Town 70 to 100 lpcd
Rural Part 55 lpcd
At consumer end
8. Reservation in Shahanoor Dam 12.45 MM3

9.Cost put to Tender Rs.117.52 Cr

10.Cost of accepted Tender Rs. 106.73 Cr

11 Contractor M / s Nagarjuna Const. Co. Ltd. Hyderabad

12.Hudco Loan granted / sanctioned Rs. 78.00 Cr

13.Time Limit of contract October 2004 With extension


Tender was floated for all allied works of this scheme. It included laying of pipe lines with cost of pipes, construction of elevated service reservoirs, treatment plant and other necessary works costing to Rs.117.524 Cr. Offer of M/s. Nagarjuna Const. Co. Ltd. Hydrabad was 9.18 % below and was approved by Pradhikaran being a lowest one
Before starting of work brief information regarding the scheme works were given to Hon. MLA, Sarpanch of all Gram Panchayats, all Panchayat Sameette Members, both Municipal Council members and Presidents of the councils, both Tahsildars, in the meeting held on dated 10.04.1999 at Maheshwary Bhawan Daryapur. Necessary land for construction of Elevated service reservoirs in the villages and towns were demanded to the members of concerned villages to avoid delay in starting the works, and huge response got in the meeting. Most of the Sarpanch handed over the open space for construction of reservoirs.
Bhoomeepoojan ceremony of this scheme was celebrated at the hands of the Hon. State Chief Minister and Hon. Minister WSSD on dated 26.05.1999





Sub Works of Scheme

1. Working Survey: Contractor carried out the working survey of all network with hydraulic designs, got it approved from M.J.P. Circle, Amravati.

2. Construction of Raw Water Sump:-A tapping to the existing canal at chainage 180 m was constructed by creating a separate head regulator and then leading main 900 mm dia. D.I., for about 90 m by gravity to 10 lakh lit capacity RCC raw water sump.

3. Raw Water Gravity main:- 800 mm dia D.I. K9 of 714 m length pipe line is laid from raw water sump to Water Treatment Plant.

4. Water Treatment Plant:- 50 MLD capacity water treatment plant is constructed near Shahanoor Dam with its all allied works. Also pure water sump of 50-lakh lit.capacity is constructed. Plant capacity of all the units have been checked for 20% overloading.

5. Principal Gravity Main: - From water treatment plant to all Master Balancing Reservoirs (MBR), Pure Water Gravity Main (PGM) of 900 mm dia DI- K9 to 150 mm dia. are laid. Overall length of pipes is 112 km. Only IVC sluice and air valves were used.

6. Hydraulic design was checked from Dr. Bhave VRCE Nagpur.

7. MBRs and ESRs: -11 no. of 25 m. staging height MBRs and 98 no. of Elevated Service Reservoirs having 12m staging are constructed in urban part and Rural part i.e. 156 villages. For proper zoning, effective maintenance and better services, minimum two outlets are provided to each ESRs and all MBRs.

8. Pure Water Gravity Main: -From 9 MBRs. constructed in rural part are connected with 250 mm to 80 mm dia DI and CI pipes to 98 ESRs constructed in Rural part. Due to metallic line network leakages are bear minimum. Also reliability of water supply is increased, and maintenance cost of pipeline is reduced. From the date of commissioning in 4-2002, water supply is uninterruptedly made available to all the beneficiaries.

9. Leading Mains :-From Urban MBRs to urban ESRs 450 to 80 mm dia DI and CI pipelines are laid for both the towns and length of laid pipe lines are 7.20 Km.

10. Distribution System For Towns:-450 to 80 mm dia CI pipe lines are laid in both the towns having total length of 77 Km.



11. Rural Distribution:-As per tender provisions only 122 km lines were proposed as a distribution lines which was quite inadequate. Detailed survey was carried out, during execution with computer drawing. All details are marked on drawing such as contours, roads, temples etc. As per detailed survey hydraulic designs are prepared on computers. According to hydraulic designs, length of 390 km for distribution system was found suitable. Hence, excess quantity proposal got approved from competent authorities. Sanctioned scheme was based on water distribution with public stand post. It is common experience that revenue realization in such system is quite inefficient. It was therefore proposed that, the distribution of water supply shall be on house connection basis and the comparative economics of the two types of distribution systems was worked out. Govt. approved distribution on house connection basis as a special case, being economical. The distribution system was then rearranged to individual house connections. Network of PVC lines are extended, so that each consumer can get the connection with only one GI pipe. It has increased the Level of Service and beneficiaries happily accepted to bear the expenditure of connection and other material. Govt. directed to collect popular contribution for increase in the level of service. Prospective consumers happily paid popular contribution of Rs. 100 per connection. MJP Engineers have done good IEC work in the villages and convinced the villagers about the policy. They also accepted to pay the connection deposit Rs.500 per connection. The charge of water supply was accepted at Rs. 50 per month. This was happening first time in case of Regional Water Supply Scheme.


12. Miscellaneous Works:-Construction of staff quarters, Rest houses, development of MIS system, installing wireless base stations, hand sets, mobile stations. Two Mahindra Jeeps and 11 computers were also procured through this tender for day to day activity of monitoring during construction and maintenance thereafter etc.

13. Ancillary works:- Providing Generator sets for occasional maintenance, anywhere in the pipeline, providing other machinery such as welding machine, power saw etc. were included in the tender and was procured.


Commissioning of the Scheme

The whole command area of the scheme is spread up in 3250 sq.km, hence, commissioning of the scheme was planned in to three phases. Anjangaon Town, Daryapur Town, Nimbhari zone having 7 villages and Daryapur Rural zone having 15 villages are commissioned in first phase. Yeoda zone 15 villages, Nandrun zone 18 villages and Songaon Zone 29 villages are commissioned in second phase. Khallar zone 19 villages, Arala zone 21 villages, Shingnapur Zone 23 villages and Mahimapur zone 9 villages are commissioned in third phase. From 25.11.04, Municipal Council Daryapur handed over the Daryapur town water supply scheme to Pradhikaran for day-to-day maintenance up to consumer, along with revenue collection.

House Connections in Rural area

During execution of scheme, at about every village Gramsabha was organized by MJP. During these meetings group discussion with the villagers were initiated regarding, functioning of the scheme, benefits of the scheme, proposed rates of water supply, time of supply and other difficulties during functioning etc. This exercise was carried in all villages to find out the demand, and their response regarding house connections. All villagers were very happy to pay Rs.500/-as deposit and initial monthly water charges at Rs.50/-. They also agreed to the concept of elimination of stand posts. For weaker section group connections were executed by sharing expenditure. All the connections are of only with 15 mm dia GI pipe to avoid leakage. Govt. had given the approval to the proposal of distribution based on house connection.

Main aim of the Gramsabha was to motivate the villagers for awareness and saving of valuable safe drinking water. Every consumer was ready to pay Rs. 100/- as a Lok-sahbhag as sort of popular contribution. Lok-sahabhag was insisted by the Govt. to ensure the people participation in the process of the house connections. Conceptually this is upgradation of level of service in water supply in rural area. At present there are about 17000 house connections in the rural area of the scheme. Deposits worth more than one crore are available from these house connections. Revenue from the rural area is more than 80%. Considering the cost of production, system in rural area stands in profit.

Main Features of the Schemes

1.The whole system is run by GRAVITY i.e. starting from canal tapping to consumer anywhere in the project area is totally on gravity, hence, power is not at all required.
2.Maintenance cost of the scheme is very less and RELIABILITY due to metallic lines is more than expected

3.WILLINGNESS TO PAY panipatti is highlighted due to increased level of service by way of house connections to every consumer.

4.AWARENESS in beneficiaries is seen about the saving and economical use of water. Availability of pure, sweet water has increased their HEALTH standard.

5.Execellent example of PEOPLE PARTICIPATION has been depicted by way of contribution of Loksahabhag at Rs.100/- per connection.

6.WASTAGE REDUCTION has been observed due to elimination of stand posts.

7.Existing underground 71 sources were abandoned. 505 H.P pumping machinery is now not necessary. An expenditure on energy, worth Rs. One crore per year, is not required now. There is an equivalent SAVING on electrical power.

8.INCREASE IN GROUND WATER LEVEL as extraction of water from underground is stopped.

9.Change in life pattern of the beneficiaries due to SAFE AND ASSURED WATER SUPPLY.

10.REDUCED MEDICAL EXPENCES have been reported in the recent survey conducted.


Innovative and environment friendliness of projects

156-village water supply scheme is 100% gravity scheme. It does not require any energy. Topography has been fully utilized. It is first one of its kind. Hence, implementation of hydraulics created new challenges. Total fall is more than 120 m. It is having huge velocity creation due to acceleration as the run time is also much more. Longest stretch on the main is more than 60km. To control gravity was main problem. New method was introduced with having a fine control on the system and it was fixed at the salient location on the line. It was found successful. Even with large gradient, water at the topmost MBR can be maintained at or near the FSL. This is the key to the unique operation of the system. System pressures are retained. Last village from MBR, also gets the water by pressure. Technology of control on gravity was developed for this scheme and applied. System runs 24 hours and is always full. There is no air locking.

Total area of influence of the project is 3250 sq.km. When there is water above LSL in MBR at TP hydraulics at all the points in the system is operating as designed. Supply to the villages is not continuous but it is given presently at one time. It has capacity to double the supply over a period. However, system remains always full. Technically, it is said to have attained the TRASFORMER status. Anytime desired quantity can be drawn at any point. The MJP engineers have achieved this and it is the unique technical feature of the scheme.


Maintenance of the Scheme

The scheme is under maintenance with Maharashtra Jeevan Pradhikaran Works Division Daryapur having three sub divisions .Day to day supply is made available to the consumers in the morning at 6.0 to 6.30 am daily. All networks are controlled with the help of wireless stations. A new approach to the maintenance of the Full gravity scheme has been developed. It has been found to be working very satisfactorily. 120 m is the fall from treatment works to Daryapur. Whole system operates under huge water pressure. At salient points master controls are installed. The effect of acceleration is tried to be nullified by maintaining design pressures at the control points. System runs 24 hours. In spite of huge fall in the system, Master sump at the highest level, is always full. It maintains the hydraulics as designed.
Staff required for day-to-day maintenance was already with MJP for operation and maintenance of old Six Regional schemes. MJP personnel are collecting revenue from consumers. Computerized bills are distributed to the consumers. Due to stoppage of pumping underground water, services of all pump operators are diverted to carry out billing and collection .
Presently plumbing and piping works are executed by MJP. This is to avoid probable damages of main lines. Cost of material for house connection is borne by consumer except service saddle. Pradhikaran provides Service saddles. Saddle is of Supreme make to avoid leakages and keeping uniformity.

UNIQUE FEATURES OF THE SCHEME

Largest Regional scheme in Maharashtra.
RRWS with maximum cost in Maharashtra.
Whole project area in SALINE TRACK.
TOTAL GRAVITY, first in India of its size.
Rational distribution on house connection basis. First of its kind.
Unique example of people participation.
Pradhikaran entering first time into maintenance upto consumer in rural area.
Pradhikaran getting revenue from individual houses in rural area.
Most reliable being gravity.
Less expenses being gravity.
Profit making right in the first year for rural part.
Highest HUDCO loan to any RRWS in Maharashtra.
Self-sufficient to run O&M.
Acceptance by people has reflected in more than 95% recovery.

All features are unique and taken collectively, have become eligible for entering into the records.

Unforgettable contributions

All concerned public representatives.
Maharashtra Jeevan Pradhikaran, Engineers and staff.
Nagarjun Construction Co. Management and staff.
Dr.Ingale,
Dr.Bhave,
Dr.Mohan,
Dr.Dhgabadgaonkar,
Dr.Kulkarni,
Prathmesh Consultants,
Electrosteel Ltd.
IVI
Supreme
And all beneficiaries

With continuous and untiring efforts of Engineers and staff, the scheme is completed. It has been upheld and supported by all Public representatives and officers at all high level. They have encouraged the happening, the new things to happen and perhaps the scheme can prove be a good model of Technoeconomical pattern having a full and willing response of the beneficiaries.

Thanks to all those, who have been well wishers of the scheme and have contributed directly and indirectly to the completion of the schemes and also in successful operation of the scheme.